A measure point always has one of five predefined statuses.
Colour | | Property | Meaning |
Green |  | Ok/Uptime | The measure point is in uptime and producing. Uptime is being counted |
Red |  | Stop | The measure point is not in uptime and stop time is being counted |
Grey |  | No schedule | Outside of scheduled time. Uptime/stops and amounts will be registered but will not be included in any reports and analyses. A schedule can always be changed afterwards to include any production outside the schedule. |
Orange |  | No run | There is no active order/article run in progress. Uptime/stops and amounts will be registered but will not be included in any reports and analyses. Time stamps for start and end of an article/order run can always be changed afterwards to include any production outside the schedule. |
Yellow |  | Changeover | Starts automatically when a new article/order is started. Also applies after a paused order. Exactly when this state is discontinued and the status switches to Ok/Uptime depends on the settings performed for changeover time. Stop time and changeover time are counted. |
Black | | No connection with machine data source | From version 21.11 and later |
General use of colours for different statuses
RS Production uses the following orders to visualize status for different things
Colour | | Property |
Grey |  | Planned |
Blue |  | Ongoing |
Black |  | Completed |
Green |  | Over target |
Red |  | Below target |